Project Reheat is done: Kitchen B and the flex room

News October 2026 · 9580 Main St.

When we opened in 2023 we had one kitchen and a waiting list. Project Reheat — our name for the buildout of the rest of the old GM cafeteria — is finished. Kitchen B and the flex room are open for member bookings.

The flex room, October 2026
The flex room, October 2026

What we started with

Next to Kitchen A sat a long room that had been storage since the GM days: steel shelving, old doors, green tile and thirty years of things nobody had thrown out.

The back corridor, before
The back corridor, before
Original green tile, thirty years of storage
Original green tile, thirty years of storage
Shelving out first
Shelving out first

Tape on the floor

Before a single wall went up, we laid the plan out in tape on the quarry tile and walked it with the people who'd actually cook there.

Layout day: the plan in tape on the original tile
Layout day: the plan in tape on the original tile
The letters go up
The letters go up

Demolition

Then the unglamorous part: shoring, demo, new plumbing and electrical through 1950s block walls, ductwork for a second hood, and a lot of hallway traffic.

Shoring in while the old walls come down
Shoring in while the old walls come down
Demo reaches the tile
Demo reaches the tile
A header goes up
A header goes up
The new opening into the flex room, framed
The new opening into the flex room, framed
Same opening, tiled and trimmed
Same opening, tiled and trimmed

Finishing

Stainless on the walls, a hand sink in every room the health department asked for one, floors, paint, and the first equipment through the door.

The walk-in cooler goes together
The walk-in cooler goes together
Hand-sink rough-in
Hand-sink rough-in
First piece of equipment rolls in
First piece of equipment rolls in
Floor prep in the flex room
Floor prep in the flex room
The corridor, finished
The corridor, finished

Kitchen B

Kitchen B is a brand-new commercial line: Viking range, convection ovens, reach-ins and a full hood, with its own entrance so two members can run at the same time without ever crossing paths. Like Kitchen A, when you book it, it's yours — no shared prep zones, no splitting oven time.

Kitchen B, ready for its first booking
Kitchen B, ready for its first booking

The flex room

The flex room is the part we're most excited about. Four butcher-block high-tops seat about two dozen; standing, comfortably more. Members use it for cooking classes, tastings, pop-ups and launch parties, and it's also available for private hire. Kitchen B comes with it.

Acoustic panels, high-tops and the stainless CCK letters
Acoustic panels, high-tops and the stainless CCK letters

With Project Reheat done, CCK has three bookable spaces — two full commercial kitchens and the flex room — in about 3,000 square feet. Want to see it? Request a tour.